Minerals







Exploration & Development of Copper in North Waziristan Agency
Sector Minerals
Total Estimated Cost Rs. 172.722 Million
Date of Commencement June 2007
Date of Completion June 2014
Project Status Ongoing
Details
Project Scope:
Enhancement of the 8 million proven reserves to more than 50 million tons through the following studies:
  • Detailed geological mapping.
  • Geophysical investigation.
  • Geophysical survey.
  • Core Drilling 7000 meters
  • Reserves estimation and preparation of bankable documents for investment by national and multi-nation companies.

Present Status:
  • 500 observation points digitized for preparation of 3D model for subsurface copper mineralization.
  • 20 Nos. geological cross sections of prospect 2,3 & 6 prepared & digitized.
  • 100 meter electrode spacing data of I.P. survey for various depth levels digitized to evolve 3D I.P. data model.
  • It has been planned to conduct 2500 meter core drilling on Shinkai copper Prospects in first phase in collaboration with another government organization.
  • After procurement of drilling accessories, drilling rigs along-with other accessories and staff at Shinkai Copper site North Waziristan Agency will be mobilized for the required core drilling.
  • Since May 2009, physical work is suspended on the project, due to law & order situation in the area.