Construction of 19 km shingle roads in Coal bearing areas of FR Peshawar,FR Kohat, Khyber and Orakzai Agencies (FATA-DA BoD/09/12/2011)
Sector Minerals
Total Estimated Cost Rs. 199.765 Million
Date of Commencement December 2011
Date of Completion June 2013
Project Status Ongoing
Details
Project Scope:

Construction of 19 km shingle roads in Coal bearing areas of FR Peshawar,FR Kohat, Khyber and Orakzai Agencies with following breakup:

  1. Construction of 08 Km shingle road from Baza to Abudag coal bearing area, Orakzai Agency. (Rs. 99.227 million)
  2. Construction of 1.5 Km shingle road from Bazikhel to coal bearing area of Baramai & Qasim khel, Dara Adam Khel, FR Kohat. (Rs.18.750 million)
  3. Construction of 02 Km shingle road from Kohat-Peshawar highway to Coal mines at Ranjo-Qasim Khel, Dara Adam Khel, FR Kohat. (Rs. 21.724 million)
  4. Construction of 02 Km shingle road from Kamar Mela to Sara Khwa coal bearing areas of Kala Khel, Bara Tehsil, Khyber Agency.( Rs. 24.553 million)
  5. Construction of 3 Km shingle road from Musa Dara to Coal mines of Janah Kor, FR Peshawar.( Rs. 29.861 million)
Present Status:
  • Funds to the extent of Rs. 80.559 million have been transferred to C & W division Orakzai Agency. 20% earth work has been completed.
  • Funds to the extent of Rs. 15.00 million have been transferred to C & W division Orakzai Agency. 80% Earth work and 30% Structure work has been completed.
  • Funds to the extent of Rs. 15.006 million transferred to the concerned C & W division. 75% Earth work and 35% Structure work on km-1 has been completed.
  • Funds to the extent of Rs. 13.00 million were transferred to the concerned C & W division. 42% Earth work completed.
  • Funds to the extent of Rs. 23.000 million have been transferred to the concerned C & W division. 50% Earth work completed on km-1.