Zao Small Dam in Khyber Agency
Sector Small Dams/Power
Total Estimated Cost Rs. 69.070 Million
Date of Commencement July, 2011
Date of Completion June, 2013
Project Status Ongoing
Details
Project Scope:

The project consists of 85 ft high earth core Rock fill dam with a gross storage of 800 Aft. The project completion will benefit 250 acres of new land beside development of Fish culture.


Present Status:

The contract for execution has been awarded to a local contracting firm M/S Shoukat Khan & Co. For detailed construction supervision the services of M/S BAK, Consulting Engineer & M/S AGES Consultants (JV) has been hired.

Physical activities on the project had commenced from July, 2011. So far, 45% physical progress has been achieved. The Project is expected to be completed by 30th June, 2013.

Feedback
Name *
Email *
Contact No
Address
City *
Agency

Do you believe that this project is beneficial for the people of this area?





Are you satisfied with the quality of work?






Do you think that work on this project is progressing fast?





Comments / Remarks

© 2007-13     FATA Development Authority, Peshawar.